The ex-ILVA Taranto blast furnaces are fully shut down, Maurizio Saitta, general manager of Acciaieria d'Italia, told unions on Friday, according to ANSA English.
Saitta told unions at the labour ministry, during a meeting on the temporary layoff programme, that nothing was running as of that morning. According to him, every facility in the hot section has been closed.
The shutdown process began on Tuesday, after the Court of Cassation last week rejected appeals by government-appointed administrators and ADI S. p. A. against closing the hot area.
In July, a Milan court ruled the site must close on health grounds, after a motion from a child with a rare genetic mutation and members of a parents' association. The court said hot-area activity must stop within three months unless all asbestos is removed and particulate emissions are brought within safe limits.
The plant's future, its planned electric decarbonization and thousands of jobs there and at suppliers are now highly uncertain.
According to media reports, a consortium led by Federacciai that had shown interest decided not to bid for the cold-rolled production area; binding bids are due November 8.
Jindal, CE industries and Flacks have shown interest in purchasing the plant, and given steel's strategic importance, Premier Giorgia Meloni's government has not excluded State involvement.
Prosecutors last week requested house arrest for former AdI President and CEO Lucia Morselli, former plant director Alessandro Labile and ISPRA's Francesco Astorri over potentially cancer-causing emissions in 2022-23.
AdI was placed under State-controlled administration early in 2024 after ArcelorMittal's ownership ended acrimoniously; Taranto was once Europe's biggest steelworks and is linked to high cancer rates.