Protective structures at 26 substations in the Kyiv region are 55% complete, Minister of Restoration, Infrastructure and Transport Mykola Kalashnyk said, according to Ukrinform. The figure was 40.02% when he left the post on July 16, he said.
Between July 16 and October 5, progress rose from 40.02% to 46.75%, an average of about 0.6 percentage points a week, Kalashnyk said. On October 5, he said, the Prime Minister-led Coordination Center flagged the risk of missing the deadline in Protocol No. 15, after which the ministry took separate coordination of the Kyiv region.
Work has continued despite a shortage of money, Kalashnyk said, and since that coordination the completion rate has risen by an average of 1.6 percentage points each week.
On October 13 the Kyiv Regional Military Administration began transferring the facilities to the Agency for Restoration to finish construction, Kalashnyk said. The Agency for Restoration will pick the contractor and be responsible for completing the work, connecting the facilities and ensuring power transmission, with an audit by the State Audit Service, he said.
Kalashnyk said advance payments total UAH 911.44 million: UAH 621.34 million during his tenure and UAH 290.10 million since July 17.
The 2026 budget allocates UAH 67.6 billion for resilience plans, with roughly UAH 60 billion more needed to finish current projects and build the next phase, according to the facts provided.